docs(14-05): complete SQLite-to-Postgres migration script plan
- SUMMARY.md with execution results - STATE.md updated with plan 05 completion - ROADMAP.md updated with phase 14 progress - DB-04 requirement marked complete
This commit is contained in:
@@ -2,10 +2,10 @@
|
||||
gsd_state_version: 1.0
|
||||
milestone: v2.0
|
||||
milestone_name: Platform Foundation
|
||||
status: planning
|
||||
stopped_at: null
|
||||
last_updated: "2026-04-03"
|
||||
last_activity: 2026-04-03 — v2.0 roadmap created (Phases 14-18)
|
||||
status: executing
|
||||
stopped_at: Completed 14-05-PLAN.md
|
||||
last_updated: "2026-04-04T10:28:29Z"
|
||||
last_activity: 2026-04-04 — Completed 14-05 SQLite-to-Postgres migration script
|
||||
progress:
|
||||
total_phases: 5
|
||||
completed_phases: 0
|
||||
@@ -26,9 +26,9 @@ See: .planning/PROJECT.md (updated 2026-04-03)
|
||||
## Current Position
|
||||
|
||||
Phase: 14 of 18 (PostgreSQL Migration)
|
||||
Plan: 0 of ? in current phase
|
||||
Status: Ready to plan
|
||||
Last activity: 2026-04-03 — v2.0 roadmap created (Phases 14-18)
|
||||
Plan: 5 of 6 in current phase
|
||||
Status: Executing
|
||||
Last activity: 2026-04-04 — Completed 14-05 SQLite-to-Postgres migration script
|
||||
|
||||
Progress: [----------] 0% (v2.0 milestone)
|
||||
|
||||
@@ -45,7 +45,9 @@ Progress: [----------] 0% (v2.0 milestone)
|
||||
|
||||
### Decisions
|
||||
|
||||
Key decisions made during v2.0 planning:
|
||||
Key decisions made during v2.0 execution:
|
||||
- [14-05] Used postgres.js unsafe() for sequence reset DDL instead of drizzle-orm sql template
|
||||
- [14-05] Row-by-row inserts for better error diagnostics during migration
|
||||
- Platform pivot: single-user to multi-user with discovery-first approach
|
||||
- External auth provider (self-hosted, open-source) — Logto vs Authentik OPEN decision
|
||||
- SQLite to Postgres migration — required by auth provider and multi-user concurrency
|
||||
@@ -64,6 +66,6 @@ None active.
|
||||
|
||||
## Session Continuity
|
||||
|
||||
Last session: 2026-04-03
|
||||
Stopped at: v2.0 roadmap created with 5 phases (14-18) covering 30 requirements
|
||||
Last session: 2026-04-04T10:28:29Z
|
||||
Stopped at: Completed 14-05-PLAN.md
|
||||
Resume file: None
|
||||
|
||||
Reference in New Issue