docs(03-02): complete daily plan UI plan
Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
This commit is contained in:
@@ -3,15 +3,15 @@ gsd_state_version: 1.0
|
||||
milestone: v1.0
|
||||
milestone_name: milestone
|
||||
status: executing
|
||||
stopped_at: Completed 03-01-PLAN.md
|
||||
last_updated: "2026-03-16T11:31:13Z"
|
||||
last_activity: 2026-03-16 — Completed 03-01-PLAN.md (daily plan data layer)
|
||||
stopped_at: Completed 03-02-PLAN.md
|
||||
last_updated: "2026-03-16T11:39:17Z"
|
||||
last_activity: 2026-03-16 — Completed 03-02-PLAN.md (daily plan UI)
|
||||
progress:
|
||||
total_phases: 4
|
||||
completed_phases: 2
|
||||
total_plans: 10
|
||||
completed_plans: 8
|
||||
percent: 80
|
||||
completed_plans: 9
|
||||
percent: 90
|
||||
---
|
||||
|
||||
# Project State
|
||||
@@ -26,18 +26,18 @@ See: .planning/PROJECT.md (updated 2026-03-15)
|
||||
## Current Position
|
||||
|
||||
Phase: 3 of 4 (Daily Plan and Cleanliness)
|
||||
Plan: 1 of 3 in current phase -- COMPLETE
|
||||
Status: Executing Phase 3 -- Plan 01 complete, Plan 02 next
|
||||
Last activity: 2026-03-16 — Completed 03-01-PLAN.md (daily plan data layer)
|
||||
Plan: 2 of 3 in current phase -- COMPLETE
|
||||
Status: Executing Phase 3 -- Plan 02 complete, Plan 03 next
|
||||
Last activity: 2026-03-16 — Completed 03-02-PLAN.md (daily plan UI)
|
||||
|
||||
Progress: [████████--] 80%
|
||||
Progress: [█████████░] 90%
|
||||
|
||||
## Performance Metrics
|
||||
|
||||
**Velocity:**
|
||||
- Total plans completed: 8
|
||||
- Average duration: 6.9 min
|
||||
- Total execution time: 0.9 hours
|
||||
- Total plans completed: 9
|
||||
- Average duration: 6.6 min
|
||||
- Total execution time: 1.0 hours
|
||||
|
||||
**By Phase:**
|
||||
|
||||
@@ -45,11 +45,11 @@ Progress: [████████--] 80%
|
||||
|-------|-------|-------|----------|
|
||||
| 1 - Foundation | 2 | 15 min | 7.5 min |
|
||||
| 2 - Rooms and Tasks | 5 | 35 min | 7.0 min |
|
||||
| 3 - Daily Plan and Cleanliness | 1 | 5 min | 5.0 min |
|
||||
| 3 - Daily Plan and Cleanliness | 2 | 9 min | 4.5 min |
|
||||
|
||||
**Recent Trend:**
|
||||
- Last 5 plans: 02-02 (11 min), 02-03 (12 min), 02-04 (3 min), 02-05 (1 min), 03-01 (5 min)
|
||||
- Trend: Data layer plan with TDD completed in 5 min
|
||||
- Last 5 plans: 02-03 (12 min), 02-04 (3 min), 02-05 (1 min), 03-01 (5 min), 03-02 (4 min)
|
||||
- Trend: UI plan with animation and tests completed in 4 min
|
||||
|
||||
*Updated after each plan completion*
|
||||
| Phase 02 P01 | 8 | 2 tasks | 16 files |
|
||||
@@ -58,6 +58,7 @@ Progress: [████████--] 80%
|
||||
| Phase 02 P04 | 3 | 2 tasks | 5 files |
|
||||
| Phase 02 P05 | 1 | 1 task | 0 files |
|
||||
| Phase 03 P01 | 5 | 2 tasks | 10 files |
|
||||
| Phase 03 P02 | 4 | 2 tasks | 5 files |
|
||||
|
||||
## Accumulated Context
|
||||
|
||||
@@ -96,6 +97,9 @@ Recent decisions affecting current work:
|
||||
- [03-01]: watchCompletionsToday uses customSelect with readsFrom for proper stream invalidation
|
||||
- [03-01]: dailyPlanProvider uses manual StreamProvider.autoDispose (not @riverpod) due to drift Task type issue
|
||||
- [03-01]: Progress total = remaining overdue + remaining today + completedTodayCount for stable denominator
|
||||
- [03-02]: Used stream-driven completion with local _completingTaskIds Set for animation instead of AnimatedList
|
||||
- [03-02]: DailyPlanTaskRow is StatelessWidget (not ConsumerWidget) -- completion callback passed in from parent
|
||||
- [03-02]: No-tasks empty state uses dailyPlanNoTasks key for clearer daily plan context messaging
|
||||
|
||||
### Pending Todos
|
||||
|
||||
@@ -109,6 +113,6 @@ None yet.
|
||||
|
||||
## Session Continuity
|
||||
|
||||
Last session: 2026-03-16T11:31:13Z
|
||||
Stopped at: Completed 03-01-PLAN.md
|
||||
Last session: 2026-03-16T11:39:17Z
|
||||
Stopped at: Completed 03-02-PLAN.md
|
||||
Resume file: None
|
||||
|
||||
Reference in New Issue