docs: start milestone v1.2 Polish & Task Management
Define requirements (9 total: task delete, creation UX, cleanup), create roadmap (phases 8-10), and update PROJECT.md with new milestone goals. Room cover photos dropped from scope. Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
This commit is contained in:
@@ -1,46 +1,47 @@
|
||||
---
|
||||
gsd_state_version: 1.0
|
||||
milestone: v1.1
|
||||
milestone_name: Calendar & Polish
|
||||
status: completed
|
||||
stopped_at: Milestone v1.1 archived
|
||||
last_updated: "2026-03-16T23:26:00.000Z"
|
||||
last_activity: 2026-03-16 — Milestone v1.1 archived
|
||||
milestone: v1.2
|
||||
milestone_name: Polish & Task Management
|
||||
status: planning
|
||||
stopped_at: Milestone v1.2 roadmap created
|
||||
last_updated: "2026-03-18"
|
||||
last_activity: 2026-03-18 — Created v1.2 milestone with requirements and roadmap
|
||||
progress:
|
||||
total_phases: 3
|
||||
completed_phases: 3
|
||||
total_plans: 5
|
||||
completed_plans: 5
|
||||
percent: 100
|
||||
completed_phases: 0
|
||||
total_plans: 0
|
||||
completed_plans: 0
|
||||
percent: 0
|
||||
---
|
||||
|
||||
# Project State
|
||||
|
||||
## Project Reference
|
||||
|
||||
See: .planning/PROJECT.md (updated 2026-03-16)
|
||||
See: .planning/PROJECT.md (updated 2026-03-18)
|
||||
|
||||
**Core value:** Users can see what needs doing today, mark it done, and trust the app to schedule the next occurrence — without thinking about it.
|
||||
**Current focus:** Planning next milestone
|
||||
**Current focus:** v1.2 Polish & Task Management — Phase 8: Task Delete
|
||||
|
||||
## Current Position
|
||||
|
||||
Milestone: v1.1 Calendar & Polish — SHIPPED
|
||||
Status: Milestone Complete
|
||||
Last activity: 2026-03-16 — Archived milestone v1.1
|
||||
Milestone: v1.2 Polish & Task Management
|
||||
Phase: 8 — Task Delete (not yet planned)
|
||||
Status: Ready for /gsd:plan-phase 8
|
||||
Last activity: 2026-03-18 — Created v1.2 milestone
|
||||
|
||||
```
|
||||
Progress: [██████████] 100% (v1.1 shipped)
|
||||
Progress: [░░░░░░░░░░] 0% (0/3 phases)
|
||||
```
|
||||
|
||||
## Performance Metrics
|
||||
|
||||
| Metric | v1.0 | v1.1 |
|
||||
|--------|------|------|
|
||||
| Phases | 4 | 3 |
|
||||
| Plans | 13 | 5 |
|
||||
| LOC (lib) | 7,773 | 9,051 |
|
||||
| Tests | 89 | 108 |
|
||||
| Metric | v1.0 | v1.1 | v1.2 |
|
||||
|--------|------|------|------|
|
||||
| Phases | 4 | 3 | 3 planned |
|
||||
| Plans | 13 | 5 | TBD |
|
||||
| LOC (lib) | 7,773 | 9,051 | TBD |
|
||||
| Tests | 89 | 108 | TBD |
|
||||
|
||||
## Accumulated Context
|
||||
|
||||
@@ -54,11 +55,11 @@ None.
|
||||
|
||||
### Blockers/Concerns
|
||||
|
||||
- Dead code from v1.0: daily_plan_providers.dart, daily_plan_task_row.dart, progress_card.dart (DailyPlanDao still used by notification service)
|
||||
- Dead code from v1.0: daily_plan_providers.dart, daily_plan_task_row.dart, progress_card.dart (DailyPlanDao still used by notification service) — scheduled for Phase 10
|
||||
|
||||
## Session Continuity
|
||||
|
||||
Last session: 2026-03-16
|
||||
Stopped at: Milestone v1.1 archived
|
||||
Last session: 2026-03-18
|
||||
Stopped at: Milestone v1.2 roadmap created
|
||||
Resume file: None
|
||||
Next action: /gsd:new-milestone
|
||||
Next action: /gsd:plan-phase 8
|
||||
|
||||