- 05-01-SUMMARY.md: execution results with deviations, decisions, self-check
- STATE.md: current position updated to Plan 01 complete, 3 new decisions
- ROADMAP.md: Phase 5 in progress (1/2 plans complete)
- REQUIREMENTS.md: CAL-02 and CAL-05 marked complete
Archive roadmap and requirements to milestones/, evolve PROJECT.md
with validated requirements and decision outcomes, reorganize
ROADMAP.md with milestone grouping, create retrospective.
Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
- Create 04-01-SUMMARY.md documenting notification service, settings notifier, and tests
- Update STATE.md: advance to Phase 4 Plan 1 complete, add 4 decisions, record metrics
- Update ROADMAP.md Phase 4 progress to 1/3 plans complete
- Mark NOTF-01 and NOTF-02 requirements as complete in REQUIREMENTS.md
- Create 02-03-SUMMARY.md with task UI accomplishments and decisions
- Update STATE.md: plan 3/5 complete, 71% progress, task decisions
- Update ROADMAP.md: mark 02-02 and 02-03 complete, 3/5 in progress
Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>