27b1a80f29 docs(05-02): complete calendar strip UI plan
- 05-02-SUMMARY.md: calendar strip UI widgets delivered, 1 auto-fix (test migration)
- STATE.md: Phase 5 complete, 2/2 plans done, decisions recorded
- ROADMAP.md: Phase 5 marked complete (2/2 plans)
- REQUIREMENTS.md: CAL-01, CAL-03, CAL-04 marked complete
2026-03-16 21:38:06 +01:00
01de2d0f9c docs(05-01): complete calendar data layer plan — CalendarDao, providers, l10n
- 05-01-SUMMARY.md: execution results with deviations, decisions, self-check
- STATE.md: current position updated to Plan 01 complete, 3 new decisions
- ROADMAP.md: Phase 5 in progress (1/2 plans complete)
- REQUIREMENTS.md: CAL-02 and CAL-05 marked complete
2026-03-16 21:26:28 +01:00
31d4ef879b docs(05-calendar-strip): create phase plan 2026-03-16 21:14:59 +01:00