gsd_state_version, milestone, milestone_name, status, stopped_at, last_updated, last_activity, progress
| gsd_state_version | milestone | milestone_name | status | stopped_at | last_updated | last_activity | progress | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1.0 | v1.2 | Collection Power-Ups | defining_requirements | Defining requirements for v1.2 | 2026-03-16T00:00:00.000Z | 2026-03-16 -- Milestone v1.2 started |
|
Project State
Project Reference
See: .planning/PROJECT.md (updated 2026-03-16)
Core value: Make it effortless to manage gear and plan new purchases -- see how a potential buy affects your total setup weight and cost before committing. Current focus: v1.2 Collection Power-Ups
Current Position
Phase: Not started (defining requirements) Plan: — Status: Defining requirements Last activity: 2026-03-16 — Milestone v1.2 started
Progress: [░░░░░░░░░░] 0%
Accumulated Context
Decisions
(Full decision log archived in PROJECT.md Key Decisions table)
Pending Todos
- Replace planning category filter select with icon-aware dropdown (ui) — folded into v1.2
Blockers/Concerns
None active.
Session Continuity
Last session: 2026-03-16T00:00:00.000Z Stopped at: Defining requirements for v1.2 Resume file: None