gsd_state_version: 1.0
|
|
milestone: v1.0
|
|
milestone_name: MVP
|
|
status: milestone_complete
|
|
stopped_at: "v1.0 MVP shipped"
|
|
last_updated: "2026-03-15"
|
|
last_activity: 2026-03-15 — v1.0 milestone archived
|
|
progress:
|
|
total_phases: 3
|
|
completed_phases: 3
|
|
total_plans: 10
|
|
completed_plans: 10
|
|
percent: 100
|
|
---
|
|
|
|
# Project State
|
|
|
|
## Project Reference
|
|
|
|
See: .planning/PROJECT.md (updated 2026-03-15)
|
|
|
|
**Core value:** Make it effortless to manage gear and plan new purchases — see how a potential buy affects your total setup weight and cost before committing.
|
|
**Current focus:** Planning next milestone
|
|
|
|
## Current Position
|
|
|
|
Milestone v1.0 MVP shipped 2026-03-15.
|
|
All 3 phases, 10 plans complete.
|
|
Ready for next milestone planning.
|
|
|
|
Progress: [██████████] 100%
|
|
|
|
## Accumulated Context
|
|
|
|
### Decisions
|
|
|
|
Decisions logged in PROJECT.md Key Decisions table.
|
|
All v1.0 decisions have outcomes marked.
|
|
|
|
### Pending Todos
|
|
|
|
None.
|
|
|
|
### Blockers/Concerns
|
|
|
|
None active.
|
|
|
|
## Session Continuity
|
|
|
|
Last session: 2026-03-15
|
|
Stopped at: v1.0 milestone complete
|
|