gsd_state_version: 1.0
milestone: v2.0
milestone_name: Platform Foundation
status: planning
stopped_at: null
last_updated: "2026-04-03"
last_activity: 2026-04-03 — v2.0 roadmap created (Phases 14-18)
progress:
total_phases: 5
completed_phases: 0
total_plans: 0
completed_plans: 0
percent: 0
---
# Project State
## Project Reference
See: .planning/PROJECT.md (updated 2026-04-03)
**Core value:** Help people make better gear decisions — discover what others use, compare real-world data, and see how a potential buy affects your setup before committing.
**Current focus:** v2.0 Platform Foundation — Phase 14 (PostgreSQL Migration)
## Current Position
Phase: 14 of 18 (PostgreSQL Migration)
Plan: 0 of ? in current phase
Status: Ready to plan
Last activity: 2026-04-03 — v2.0 roadmap created (Phases 14-18)
Progress: [----------] 0% (v2.0 milestone)
## Performance Metrics
**Velocity:**
- Total plans completed: 0 (v2.0 milestone)
- Average duration: --
- Total execution time: --
*Updated after each plan completion*
## Accumulated Context
### Decisions
Key decisions made during v2.0 planning:
- Platform pivot: single-user to multi-user with discovery-first approach
- External auth provider (self-hosted, open-source) — Logto vs Authentik OPEN decision
- SQLite to Postgres migration — required by auth provider and multi-user concurrency
- Structured UGC only — ratings and predefined fields, no freeform text until moderation
- Separate globalItems table — not a flag on user items table
- Single-user SQLite mode diverges at v2.0 boundary
### Pending Todos
None active.
### Blockers/Concerns
- Auth provider decision (Logto vs Authentik) must be resolved before Phase 15 planning
- Phase 14 is a full schema rewrite touching 6 services, 7 routes, 19 MCP tools, all tests
## Session Continuity
Last session: 2026-04-03
Stopped at: v2.0 roadmap created with 5 phases (14-18) covering 30 requirements
Resume file: None