gsd_state_version: 1.0
milestone: v1.0
milestone_name: milestone
status: planning
stopped_at: Phase 1 context gathered
last_updated: "2026-03-14T21:10:41.234Z"
last_activity: 2026-03-14 — Roadmap created
progress:
total_phases: 3
completed_phases: 0
total_plans: 0
completed_plans: 0
percent: 0
---
# Project State
## Project Reference
See: .planning/PROJECT.md (updated 2026-03-14)
**Core value:** Make it effortless to manage gear and plan new purchases — see how a potential buy affects your total setup weight and cost before committing.
**Current focus:** Phase 1: Foundation and Collection
## Current Position
Phase: 1 of 3 (Foundation and Collection)
Plan: 0 of 0 in current phase
Status: Ready to plan
Last activity: 2026-03-14 — Roadmap created
Progress: [░░░░░░░░░░] 0%
## Performance Metrics
**Velocity:**
- Total plans completed: 0
- Average duration: -
- Total execution time: 0 hours
**By Phase:**
| Phase | Plans | Total | Avg/Plan |
|-------|-------|-------|----------|
| - | - | - | - |
**Recent Trend:**
- Last 5 plans: -
- Trend: -
*Updated after each plan completion*
## Accumulated Context
### Decisions
Decisions are logged in PROJECT.md Key Decisions table.
Recent decisions affecting current work:
- [Roadmap]: 3-phase coarse structure — Collection, Threads, Setups+Dashboard
- [Roadmap]: Setups and Dashboard combined into single phase (coarse granularity)
### Pending Todos
None yet.
### Blockers/Concerns
- Verify @hono/zod-validator supports Zod 4.x before starting Phase 1. If not, pin Zod 3.23.x.
- Confirm Bun fullstack vs. Vite proxy dev setup pattern before project scaffolding.
## Session Continuity
Last session: 2026-03-14T21:10:41.232Z
Stopped at: Phase 1 context gathered
Resume file: .planning/phases/01-foundation-and-collection/01-CONTEXT.md