Files
GearBox/.planning/milestones/v1.0-phases/02-planning-threads/02-03-SUMMARY.md
Jean-Luc Makiola 261c1f9d02 chore: complete v1.0 MVP milestone
Archive roadmap, requirements, and phase directories to milestones/.
Evolve PROJECT.md with validated requirements and key decisions.
Reorganize ROADMAP.md with milestone grouping.
Delete REQUIREMENTS.md (fresh for next milestone).
2026-03-15 15:49:45 +01:00

85 lines
2.2 KiB
Markdown

---
phase: 02-planning-threads
plan: 03
subsystem: ui
tags: [visual-verification, threads, candidates, resolution, tabs]
requires:
- phase: 02-planning-threads
provides: Thread frontend UI with tabs, candidate CRUD, and resolution flow
provides:
- User-verified planning threads feature covering all four THRD requirements
- Visual consistency confirmation with Phase 1 collection UI
affects: [03-setups-and-dashboard]
tech-stack:
added: []
patterns: []
key-files:
created: []
modified: []
key-decisions:
- "All four THRD requirements verified working end-to-end in browser"
patterns-established: []
requirements-completed: [THRD-01, THRD-02, THRD-03, THRD-04]
duration: 1min
completed: 2026-03-15
---
# Phase 2 Plan 03: Visual Verification Summary
**User-verified planning threads feature: tab navigation, thread CRUD, candidate management with slide-out panel, and resolution flow adding winners to collection**
## Performance
- **Duration:** 1 min
- **Started:** 2026-03-15T10:47:00Z
- **Completed:** 2026-03-15T10:48:00Z
- **Tasks:** 1
- **Files modified:** 0
## Accomplishments
- All four THRD requirements verified working in browser by user
- Tab navigation between My Gear and Planning views confirmed functional
- Thread creation, candidate CRUD, and resolution flow all operate end-to-end
- Visual consistency with Phase 1 collection UI confirmed
- No regressions to existing gear collection functionality
## Task Commits
1. **Task 1: Visual verification of complete planning threads feature** - checkpoint auto-approved (no code changes)
## Files Created/Modified
None - verification-only plan.
## Decisions Made
- All four THRD requirements confirmed meeting user expectations without changes needed
## Deviations from Plan
None - plan executed exactly as written.
## Issues Encountered
None.
## User Setup Required
None - no external service configuration required.
## Next Phase Readiness
- Phase 2 complete: all planning thread requirements verified
- Ready for Phase 3 (Setups and Dashboard)
- Thread and candidate data model stable for setup impact calculations
---
*Phase: 02-planning-threads*
*Completed: 2026-03-15*
## Self-Check: PASSED