3.5 KiB
3.5 KiB
phase, plan, subsystem, tags, requires, provides, affects, tech-stack, key-files, key-decisions, patterns-established, requirements-completed, duration, completed
| phase | plan | subsystem | tags | requires | provides | affects | tech-stack | key-files | key-decisions | patterns-established | requirements-completed | duration | completed | |||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 03-setups-and-dashboard | 01 | api |
|
|
|
|
|
|
|
|
|
8min | 2026-03-15 |
Phase 3 Plan 1: Setup Backend Summary
Setup CRUD API with junction table, SQL aggregation for totals, and transactional item sync
Performance
- Duration: 8 min
- Started: 2026-03-15T11:35:17Z
- Completed: 2026-03-15T11:43:11Z
- Tasks: 2 (TDD RED + GREEN)
- Files modified: 9
Accomplishments
- Setup CRUD with all 7 API endpoints working
- Junction table (setup_items) with cascade deletes on both setup and item deletion
- SQL aggregation returning itemCount, totalWeight, totalCost via COALESCE subqueries
- Full TDD with 24 new tests (13 service + 11 route), all 87 tests passing
Task Commits
Each task was committed atomically:
- Task 1: RED - Failing tests + schema -
1e4e74f(test) - Task 2: GREEN - Implementation -
0f115a2(feat)
Files Created/Modified
src/db/schema.ts- Added setups and setupItems table definitionssrc/shared/schemas.ts- Added createSetupSchema, updateSetupSchema, syncSetupItemsSchemasrc/shared/types.ts- Added CreateSetup, UpdateSetup, SyncSetupItems, Setup, SetupItem typessrc/server/services/setup.service.ts- Setup business logic with DB injectionsrc/server/routes/setups.ts- Hono API routes for all 7 setup endpointssrc/server/index.ts- Mounted setupRoutes at /api/setupstests/helpers/db.ts- Added setups and setup_items CREATE TABLE statementstests/services/setup.service.test.ts- 13 service unit teststests/routes/setups.test.ts- 11 route integration tests
Decisions Made
- syncSetupItems uses delete-all + re-insert in transaction for simplicity over diff-based sync
- SQL COALESCE ensures 0 returned for empty setups instead of null
- removeSetupItem uses raw SQL WHERE clause for compound condition (setupId + itemId)
Deviations from Plan
None - plan executed exactly as written.
Issues Encountered
None
User Setup Required
None - no external service configuration required.
Next Phase Readiness
- Setup API complete and tested, ready for frontend consumption in Plan 02
- Junction table pattern established for any future many-to-many relationships
Phase: 03-setups-and-dashboard Completed: 2026-03-15