Files
GearBox/.planning/milestones/v1.1-ROADMAP.md
Jean-Luc Makiola 407fa45280 chore: complete v1.1 milestone — Fixes & Polish
Archive v1.1 artifacts (roadmap, requirements, phases) to milestones/.
Evolve PROJECT.md with shipped requirements and new key decisions.
Reorganize ROADMAP.md with collapsed milestone groupings.
Update retrospective with v1.1 lessons.

Co-Authored-By: Claude Opus 4.6 (1M context) <noreply@anthropic.com>
2026-03-15 18:16:27 +01:00

3.8 KiB

Roadmap: GearBox

Milestones

  • v1.0 MVP -- Phases 1-3 (shipped 2026-03-15)
  • v1.1 Fixes & Polish -- Phases 4-6 (in progress)

Phases

v1.0 MVP (Phases 1-3) -- SHIPPED 2026-03-15
  • Phase 1: Foundation and Collection (4/4 plans) -- completed 2026-03-14
  • Phase 2: Planning Threads (3/3 plans) -- completed 2026-03-15
  • Phase 3: Setups and Dashboard (3/3 plans) -- completed 2026-03-15

v1.1 Fixes & Polish (In Progress)

Milestone Goal: Fix broken functionality, improve image handling UX, and replace emoji categories with Lucide icon picker.

  • Phase 4: Database & Planning Fixes - Fix threads table and planning thread creation, polish empty states
  • Phase 5: Image Handling - Fix image display and redesign upload UX with previews (completed 2026-03-15)
  • Phase 6: Category Icons - Replace emoji categories with Lucide icon picker

Phase Details

Phase 4: Database & Planning Fixes

Goal: Users can create and manage planning threads without errors Depends on: Phase 3 (v1.0 complete) Requirements: DB-01, PLAN-01, PLAN-02 Success Criteria (what must be TRUE):

  1. Running database schema push creates the threads table (and any other missing tables) without errors
  2. User can create a new planning thread from the planning tab and it appears in the thread list
  3. User sees a clear, polished empty state with a call-to-action when no planning threads exist Plans: 2 plans

Plans:

  • 04-01-PLAN.md — Database schema fix and backend thread API with categoryId
  • 04-02-PLAN.md — Frontend planning tab overhaul (modal, empty state, pill tabs, category filter)

Phase 5: Image Handling

Goal: Users can see and manage gear images throughout the app Depends on: Phase 4 Requirements: IMG-01, IMG-02, IMG-03, IMG-04 Success Criteria (what must be TRUE):

  1. User can see previously uploaded images displayed correctly on item detail views
  2. Gear collection cards show item images (or a placeholder when no image exists)
  3. Item form displays an image preview area at the top with a placeholder icon when no image is set
  4. User can upload an image by clicking the placeholder area, and the preview updates immediately Plans: 2 plans

Plans:

  • 05-01-PLAN.md — Fix image display bug and redesign ImageUpload as hero preview area
  • 05-02-PLAN.md — Add card image placeholders and setup thumbnails

Phase 6: Category Icons

Goal: Categories use clean Lucide icons instead of emoji Depends on: Phase 4 Requirements: CAT-01, CAT-02, CAT-03 Success Criteria (what must be TRUE):

  1. User can browse and select a Lucide icon from a picker when creating or editing a category
  2. Category icons render as Lucide icons everywhere they appear (cards, headers, lists, dashboard)
  3. Existing emoji-based categories display as equivalent Lucide icons without manual user intervention Plans: 3 plans

Plans:

  • 06-01-PLAN.md — Backend schema migration (emoji to icon), install lucide-react, create icon data and LucideIcon component
  • 06-02-PLAN.md — Build IconPicker component, update category create/edit components
  • 06-03-PLAN.md — Update all display components to Lucide icons, delete old emoji code

Progress

Execution Order: Phases execute in numeric order: 4 -> 5 -> 6

Phase Milestone Plans Complete Status Completed
1. Foundation and Collection v1.0 4/4 Complete 2026-03-14
2. Planning Threads v1.0 3/3 Complete 2026-03-15
3. Setups and Dashboard v1.0 3/3 Complete 2026-03-15
4. Database & Planning Fixes v1.1 1/2 In progress -
5. Image Handling 2/2 Complete 2026-03-15 -
6. Category Icons v1.1 0/3 Not started -