gsd_state_version: 1.0
|
|
milestone: v1.0
|
|
milestone_name: milestone
|
|
status: Ready to execute
|
|
stopped_at: Completed 11-01-PLAN.md
|
|
last_updated: "2026-03-24T08:49:28.728Z"
|
|
progress:
|
|
total_phases: 4
|
|
completed_phases: 3
|
|
total_plans: 6
|
|
completed_plans: 5
|
|
---
|
|
|
|
# Project State
|
|
|
|
## Project Reference
|
|
|
|
See: .planning/PROJECT.md (updated 2026-03-18)
|
|
|
|
**Core value:** Users can see what needs doing today, mark it done, and trust the app to schedule the next occurrence — without thinking about it.
|
|
**Current focus:** Phase 11 — issue-3-tasks-management-allow-task-checking-anytime-and-pre-populate-recurring-tasks
|
|
|
|
## Current Position
|
|
|
|
Phase: 11 (issue-3-tasks-management-allow-task-checking-anytime-and-pre-populate-recurring-tasks) — EXECUTING
|
|
Plan: 2 of 2
|
|
|
|
## Performance Metrics
|
|
|
|
| Metric | v1.0 | v1.1 | v1.2 |
|
|
|--------|------|------|------|
|
|
| Phases | 4 | 3 | 3 planned |
|
|
| Plans | 13 | 5 | TBD |
|
|
| LOC (lib) | 7,773 | 9,051 | TBD |
|
|
| Tests | 89 | 108 | TBD |
|
|
| Phase 08-task-delete P01 | 9 | 2 tasks | 11 files |
|
|
| Phase 08-task-delete P02 | 2 | 2 tasks | 3 files |
|
|
| Phase 09-task-creation-ux P01 | 2 | 1 tasks | 4 files |
|
|
| Phase 10-dead-code-cleanup P01 | 5 | 2 tasks | 4 files |
|
|
| Phase 11-issue-3-tasks-management-allow-task-checking-anytime-and-pre-populate-recurring-tasks P01 | 219 | 2 tasks | 4 files |
|
|
|
|
## Accumulated Context
|
|
|
|
### Decisions
|
|
|
|
Decisions archived to PROJECT.md Key Decisions table.
|
|
|
|
- [Phase 08-task-delete]: isActive uses BoolColumn.withDefault(true) so existing rows are automatically active after migration without backfill
|
|
- [Phase 08-task-delete]: Migration uses from==2 (not from<3) for addColumn to avoid duplicate-column error when createTable already includes isActive in current schema definition
|
|
- [Phase 08-task-delete]: Migration tests updated to only test v1->v3 and v2->v3 paths since AppDatabase.schemaVersion=3 always migrates to v3
|
|
- [Phase 08-task-delete]: smartDeleteTask kept separate from deleteTask to preserve existing hard-delete path for cascade/other uses
|
|
- [Phase 08-task-delete]: Delete button placed after history section with divider, visible only in edit mode
|
|
- [Phase 09-task-creation-ux]: Picker is single source of truth: _resolveFrequency() reads from picker always; _ShortcutFrequency enum handles bidirectional sync via toPickerValues()/fromPickerValues()
|
|
- [Phase 10-dead-code-cleanup]: DailyPlanDao kept in database.dart — still used by settings service; only the three presentation layer files were deleted
|
|
- [Phase 10-dead-code-cleanup]: TaskWithRoom retained in daily_plan_models.dart — actively used by calendar_dao.dart, calendar_providers.dart, and related calendar files
|
|
- [Phase 11-issue-3-tasks-management-allow-task-checking-anytime-and-pre-populate-recurring-tasks]: D-01: Remove isFuture/canComplete restrictions — checkboxes always enabled across all UI; calendar_task_row.dart unchanged (caller was applying restriction)
|
|
- [Phase 11-issue-3-tasks-management-allow-task-checking-anytime-and-pre-populate-recurring-tasks]: D-02: When completing on non-due day, use today as baseDate for nextDueDate calculation (todayStart == taskDueDay pattern)
|
|
|
|
### Pending Todos
|
|
|
|
None.
|
|
|
|
### Roadmap Evolution
|
|
|
|
- Phase 11 added: Issue #3 Tasks Management — Allow task checking anytime and pre-populate recurring tasks
|
|
|
|
### Blockers/Concerns
|
|
|
|
None.
|
|
|
|
## Session Continuity
|
|
|
|
Last session: 2026-03-24T08:49:28.726Z
|
|
Stopped at: Completed 11-01-PLAN.md
|
|
Resume file: None
|
|