gsd_state_version: 1.0
|
|
milestone: v1.0
|
|
milestone_name: milestone
|
|
status: planning
|
|
stopped_at: Completed 05-calendar-strip 05-01-PLAN.md
|
|
last_updated: "2026-03-16T20:25:46.918Z"
|
|
last_activity: 2026-03-16 — Roadmap for v1.1 written (phases 5-7)
|
|
progress:
|
|
total_phases: 3
|
|
completed_phases: 0
|
|
total_plans: 2
|
|
completed_plans: 1
|
|
percent: 0
|
|
---
|
|
|
|
# Project State
|
|
|
|
## Project Reference
|
|
|
|
See: .planning/PROJECT.md (updated 2026-03-16)
|
|
|
|
**Core value:** Users can see what needs doing today, mark it done, and trust the app to schedule the next occurrence — without thinking about it.
|
|
**Current focus:** v1.1 Calendar & Polish — Phase 5: Calendar Strip
|
|
|
|
## Current Position
|
|
|
|
Phase: 5 — Calendar Strip
|
|
Plan: 1/2 complete (Plan 01 done)
|
|
Status: In Progress
|
|
Last activity: 2026-03-16 — Completed Phase 5 Plan 01 (CalendarDao + providers)
|
|
|
|
```
|
|
Progress: [█████░░░░░] 50% (1/2 plans in Phase 5)
|
|
```
|
|
|
|
## Performance Metrics
|
|
|
|
| Metric | v1.0 | v1.1 |
|
|
|--------|------|------|
|
|
| Phases | 4 | 3 planned |
|
|
| Plans | 13 | TBD |
|
|
| LOC (lib) | 7,773 | TBD |
|
|
| Tests | 89 | TBD |
|
|
| Phase 05-calendar-strip P01 | 5 | 2 tasks | 10 files |
|
|
|
|
## Accumulated Context
|
|
|
|
### Decisions
|
|
|
|
| Decision | Rationale |
|
|
|----------|-----------|
|
|
| Calendar strip replaces daily plan home screen | v1.1 goal per PROJECT.md — not additive, the stacked overdue/today/upcoming sections are removed |
|
|
| Phase 5 before Phase 6 and 7 | Calendar strip is the primary UI surface; history and sorting operate within or alongside it |
|
|
| Phase 6 and 7 both depend on Phase 5 only | History and sorting are independent of each other — could execute in either order |
|
|
| HIST-01 and HIST-02 in same phase | Data layer (HIST-01) is only 1-2 DAO additions; grouping with the UI (HIST-02) keeps the phase coherent |
|
|
| Used NotifierProvider<SelectedDateNotifier> instead of deprecated StateProvider | Riverpod 3.x removed StateProvider; NotifierProvider is the correct replacement |
|
|
| calendarDayProvider fetches overdue tasks with .first in asyncMap when isToday | Consistent with dailyPlanProvider pattern; avoids combining two streams |
|
|
| watchTasksForDate sorts alphabetically by task name | Same-day tasks have no meaningful time-based order; alpha sort is deterministic and user-friendly |
|
|
|
|
### Pending Todos
|
|
|
|
None.
|
|
|
|
### Blockers/Concerns
|
|
|
|
- The existing HomeScreen (daily plan with overdue/today/upcoming) will be replaced entirely in Phase 5. Plan 02 will handle migrating or removing the dailyPlanProvider reference.
|
|
- CAL-05 resolved: new CalendarDao created with date-parameterized queries; overdue tasks shown only when viewing today.
|
|
|
|
## Session Continuity
|
|
|
|
Last session: 2026-03-16T20:25:46.916Z
|
|
Stopped at: Completed 05-calendar-strip 05-01-PLAN.md
|
|
Resume file: None
|
|
Next action: `/gsd:plan-phase 5`
|