milestone: v1.0
|
|
milestone_name: milestone
|
|
status: executing
|
|
stopped_at: Completed 02-03-PLAN.md
|
|
last_updated: "2026-03-15T21:09:52Z"
|
|
last_activity: 2026-03-15 — Completed 02-03-PLAN.md (task UI, form, list screen, providers)
|
|
progress:
|
|
total_phases: 4
|
|
completed_phases: 1
|
|
total_plans: 7
|
|
completed_plans: 5
|
|
percent: 71
|
|
---
|
|
|
|
# Project State
|
|
|
|
## Project Reference
|
|
|
|
See: .planning/PROJECT.md (updated 2026-03-15)
|
|
|
|
**Core value:** Users can see what needs doing today, mark it done, and trust the app to schedule the next occurrence — without thinking about it.
|
|
**Current focus:** Phase 2: Rooms and Tasks
|
|
|
|
## Current Position
|
|
|
|
Phase: 2 of 4 (Rooms and Tasks)
|
|
Plan: 3 of 5 in current phase -- COMPLETE
|
|
Status: Executing Phase 2 -- 02-03 complete, ready for 02-04
|
|
Last activity: 2026-03-15 — Completed 02-03-PLAN.md (task UI, form, list screen, providers)
|
|
|
|
Progress: [███████---] 71%
|
|
|
|
## Performance Metrics
|
|
|
|
**Velocity:**
|
|
- Total plans completed: 5
|
|
- Average duration: 9.0 min
|
|
- Total execution time: 0.75 hours
|
|
|
|
**By Phase:**
|
|
|
|
| Phase | Plans | Total | Avg/Plan |
|
|
|-------|-------|-------|----------|
|
|
| 1 - Foundation | 2 | 15 min | 7.5 min |
|
|
| 2 - Rooms and Tasks | 3 | 31 min | 10.3 min |
|
|
|
|
**Recent Trend:**
|
|
- Last 5 plans: 01-01 (7 min), 01-02 (8 min), 02-01 (8 min), 02-02 (11 min), 02-03 (12 min)
|
|
- Trend: slightly increasing (UI plans take longer than data/scaffold)
|
|
|
|
*Updated after each plan completion*
|
|
| Phase 02 P01 | 8 | 2 tasks | 16 files |
|
|
| Phase 02 P02 | 11 | 2 tasks | 14 files |
|
|
| Phase 02 P03 | 12 | 2 tasks | 8 files |
|
|
|
|
## Accumulated Context
|
|
|
|
### Decisions
|
|
|
|
Decisions are logged in PROJECT.md Key Decisions table.
|
|
Recent decisions affecting current work:
|
|
|
|
- [Pre-phase]: Riverpod 3.3 requires Flutter 3.41+ — verify before scaffolding
|
|
- [Pre-phase]: All due dates stored as date-only (calendar day), not DateTime — enforce from first migration
|
|
- [Pre-phase]: German-only UI for MVP; localization infrastructure (ARB + AppLocalizations) required from Phase 1 even with one locale
|
|
- [Pre-phase]: riverpod_lint must be active before any feature code — catches ref.watch outside build() at analysis time
|
|
- [Pre-phase]: drift_dev make-migrations workflow must be established in Phase 1 — recovery cost is data loss
|
|
- [01-01]: Pinned drift/drift_dev to 2.31.0 for analyzer ^9.0.0 compatibility with riverpod_generator 4.0.3
|
|
- [01-01]: Generated Riverpod 3 provider named themeProvider (not themeNotifierProvider) per new naming convention
|
|
- [Phase 01-02]: Used themeProvider (Riverpod 3 naming) instead of themeNotifierProvider referenced in plan
|
|
- [02-01]: Scheduling functions are top-level pure functions with DateTime today parameter for testability
|
|
- [02-01]: Calendar-anchored intervals use anchorDay nullable field for month-clamping memory
|
|
- [02-01]: RoomWithStats computed via asyncMap on watchAllRooms stream, not a custom SQL join
|
|
- [02-01]: Templates stored as Dart const map for type safety, not JSON assets
|
|
- [02-01]: detectRoomType uses contains-based matching with alias map
|
|
- [Phase 02]: Scheduling functions are top-level pure functions with DateTime today parameter for testability
|
|
- [Phase 02]: Calendar-anchored intervals use anchorDay nullable field for month-clamping memory
|
|
- [Phase 02]: Templates stored as Dart const map for type safety, not JSON assets
|
|
- [02-02]: ReorderableBuilder<Widget> with typed onReorder callback for drag-and-drop grid
|
|
- [02-02]: Long-press context menu (bottom sheet) for edit/delete on room cards
|
|
- [02-02]: Provider override pattern in tests to decouple from database dependency
|
|
- [02-03]: tasksInRoomProvider defined as manual StreamProvider.family due to riverpod_generator InvalidTypeException with drift Task type
|
|
- [02-03]: Frequency selector uses ChoiceChip Wrap layout for 10 presets plus custom option
|
|
- [02-03]: TaskRow uses ListTile with middle-dot separator between relative date and frequency label
|
|
|
|
### Pending Todos
|
|
|
|
None yet.
|
|
|
|
### Blockers/Concerns
|
|
|
|
- ~~[Research]: Recurrence policy edge cases not fully specified~~ — **RESOLVED** in 2-CONTEXT.md: calendar-anchored intervals clamp to last day with anchor memory, day-count intervals roll forward. Next due from original due date. Catch-up skips to next future date.
|
|
- [Research]: Notification time configuration (user-adjustable vs hardcoded) not resolved. Decide before Phase 4 planning.
|
|
- ~~[Research]: First-launch template seeding UX (silent vs prompted) not resolved~~ — **RESOLVED** in 2-CONTEXT.md: post-creation prompt with all templates unchecked. Room type is optional, detected from name. Custom rooms skip templates entirely.
|
|
|
|
## Session Continuity
|
|
|
|
Last session: 2026-03-15T21:09:52Z
|
|
Stopped at: Completed 02-03-PLAN.md
|
|
Resume file: None
|