Jean-Luc Makiola 6ad42536e9 docs(02-05): complete Phase 2 verification gate plan
- Auto-approved verification checkpoint (59/59 tests, dart analyze clean)
- Phase 2 marked complete in ROADMAP.md (5/5 plans)
- STATE.md updated for Phase 3 readiness

Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
2026-03-15 22:24:45 +01:00

109 lines
5.2 KiB
Markdown

---
gsd_state_version: 1.0
milestone: v1.0
milestone_name: milestone
status: executing
stopped_at: Completed 02-05-PLAN.md
last_updated: "2026-03-15T21:22:53Z"
last_activity: 2026-03-15 — Completed 02-05-PLAN.md (Phase 2 verification gate passed)
progress:
total_phases: 4
completed_phases: 2
total_plans: 7
completed_plans: 7
percent: 100
---
# Project State
## Project Reference
See: .planning/PROJECT.md (updated 2026-03-15)
**Core value:** Users can see what needs doing today, mark it done, and trust the app to schedule the next occurrence — without thinking about it.
**Current focus:** Phase 3: Daily Plan and Cleanliness
## Current Position
Phase: 2 of 4 (Rooms and Tasks) -- COMPLETE
Plan: 5 of 5 in current phase -- COMPLETE
Status: Phase 2 complete -- ready for Phase 3 planning
Last activity: 2026-03-15 — Completed 02-05-PLAN.md (Phase 2 verification gate passed)
Progress: [██████████] 100%
## Performance Metrics
**Velocity:**
- Total plans completed: 7
- Average duration: 7.3 min
- Total execution time: 0.9 hours
**By Phase:**
| Phase | Plans | Total | Avg/Plan |
|-------|-------|-------|----------|
| 1 - Foundation | 2 | 15 min | 7.5 min |
| 2 - Rooms and Tasks | 5 | 35 min | 7.0 min |
**Recent Trend:**
- Last 5 plans: 02-01 (8 min), 02-02 (11 min), 02-03 (12 min), 02-04 (3 min), 02-05 (1 min)
- Trend: verification-only plan completed in 1 min (auto-approved checkpoint)
*Updated after each plan completion*
| Phase 02 P01 | 8 | 2 tasks | 16 files |
| Phase 02 P02 | 11 | 2 tasks | 14 files |
| Phase 02 P03 | 12 | 2 tasks | 8 files |
| Phase 02 P04 | 3 | 2 tasks | 5 files |
| Phase 02 P05 | 1 | 1 task | 0 files |
## Accumulated Context
### Decisions
Decisions are logged in PROJECT.md Key Decisions table.
Recent decisions affecting current work:
- [Pre-phase]: Riverpod 3.3 requires Flutter 3.41+ — verify before scaffolding
- [Pre-phase]: All due dates stored as date-only (calendar day), not DateTime — enforce from first migration
- [Pre-phase]: German-only UI for MVP; localization infrastructure (ARB + AppLocalizations) required from Phase 1 even with one locale
- [Pre-phase]: riverpod_lint must be active before any feature code — catches ref.watch outside build() at analysis time
- [Pre-phase]: drift_dev make-migrations workflow must be established in Phase 1 — recovery cost is data loss
- [01-01]: Pinned drift/drift_dev to 2.31.0 for analyzer ^9.0.0 compatibility with riverpod_generator 4.0.3
- [01-01]: Generated Riverpod 3 provider named themeProvider (not themeNotifierProvider) per new naming convention
- [Phase 01-02]: Used themeProvider (Riverpod 3 naming) instead of themeNotifierProvider referenced in plan
- [02-01]: Scheduling functions are top-level pure functions with DateTime today parameter for testability
- [02-01]: Calendar-anchored intervals use anchorDay nullable field for month-clamping memory
- [02-01]: RoomWithStats computed via asyncMap on watchAllRooms stream, not a custom SQL join
- [02-01]: Templates stored as Dart const map for type safety, not JSON assets
- [02-01]: detectRoomType uses contains-based matching with alias map
- [Phase 02]: Scheduling functions are top-level pure functions with DateTime today parameter for testability
- [Phase 02]: Calendar-anchored intervals use anchorDay nullable field for month-clamping memory
- [Phase 02]: Templates stored as Dart const map for type safety, not JSON assets
- [02-02]: ReorderableBuilder<Widget> with typed onReorder callback for drag-and-drop grid
- [02-02]: Long-press context menu (bottom sheet) for edit/delete on room cards
- [02-02]: Provider override pattern in tests to decouple from database dependency
- [02-03]: tasksInRoomProvider defined as manual StreamProvider.family due to riverpod_generator InvalidTypeException with drift Task type
- [02-03]: Frequency selector uses ChoiceChip Wrap layout for 10 presets plus custom option
- [02-03]: TaskRow uses ListTile with middle-dot separator between relative date and frequency label
- [02-04]: Template picker uses StatefulWidget (not Consumer) receiving data via constructor
- [02-04]: Room creation navigates to /rooms/$roomId (context.go) instead of context.pop to show new room
- [02-04]: Calendar-anchored intervals set anchorDay to today's day-of-month; day-count intervals set null
- [02-05]: Auto-approved verification checkpoint: dart analyze clean, 59/59 tests passing, all Phase 2 code integrated
### Pending Todos
None yet.
### Blockers/Concerns
- ~~[Research]: Recurrence policy edge cases not fully specified~~ — **RESOLVED** in 2-CONTEXT.md: calendar-anchored intervals clamp to last day with anchor memory, day-count intervals roll forward. Next due from original due date. Catch-up skips to next future date.
- [Research]: Notification time configuration (user-adjustable vs hardcoded) not resolved. Decide before Phase 4 planning.
- ~~[Research]: First-launch template seeding UX (silent vs prompted) not resolved~~ — **RESOLVED** in 2-CONTEXT.md: post-creation prompt with all templates unchecked. Room type is optional, detected from name. Custom rooms skip templates entirely.
## Session Continuity
Last session: 2026-03-15T21:22:53Z
Stopped at: Completed 02-05-PLAN.md (Phase 2 complete)
Resume file: None