gsd_state_version: 1.0
milestone: v1.0
milestone_name: MVP
status: shipped
stopped_at: v1.0 milestone complete
last_updated: "2026-03-16T20:00:00.000Z"
last_activity: 2026-03-16 — v1.0 MVP milestone shipped
progress:
total_phases: 4
completed_phases: 4
total_plans: 13
completed_plans: 13
percent: 100
---
# Project State
## Project Reference
See: .planning/PROJECT.md (updated 2026-03-16)
**Core value:** Users can see what needs doing today, mark it done, and trust the app to schedule the next occurrence — without thinking about it.
**Current focus:** v1.0 shipped — planning next milestone
## Current Position
Milestone: v1.0 MVP — SHIPPED 2026-03-16
Status: All 4 phases complete, 13/13 plans executed, 89 tests passing
Next: `/gsd:new-milestone` for v1.1
Progress: [##########] 100%
## Performance Metrics
**Velocity:**
- Total plans completed: 13
- Total execution time: ~1.3 hours
- Average duration: ~6 min/plan
**By Phase:**
| Phase | Plans | Total | Avg/Plan |
|-------|-------|-------|----------|
| 1 - Foundation | 2 | 15 min | 7.5 min |
| 2 - Rooms and Tasks | 5 | 35 min | 7.0 min |
| 3 - Daily Plan and Cleanliness | 3 | 11 min | 3.7 min |
| 4 - Notifications | 3 | 16 min | 5.3 min |
## Accumulated Context
### Decisions
All v1.0 decisions are recorded in PROJECT.md Key Decisions table with outcomes.
### Pending Todos
None.
### Blockers/Concerns
None — all v1.0 blockers resolved.
## Session Continuity
Last session: 2026-03-16
Stopped at: v1.0 milestone complete
Resume file: None