Archive v1.1 Calendar & Polish milestone artifacts (roadmap, requirements, phase directories) to milestones/. Evolve PROJECT.md with validated requirements and new key decisions. Update RETROSPECTIVE.md with v1.1 section and cross-milestone trends. Co-Authored-By: Claude Opus 4.6 <noreply@anthropic.com>
44 lines
1.5 KiB
Markdown
44 lines
1.5 KiB
Markdown
# Roadmap: HouseHoldKeaper
|
|
|
|
## Milestones
|
|
|
|
- ✅ **v1.0 MVP** — Phases 1-4 (shipped 2026-03-16)
|
|
- ✅ **v1.1 Calendar & Polish** — Phases 5-7 (shipped 2026-03-16)
|
|
|
|
## Phases
|
|
|
|
<details>
|
|
<summary>✅ v1.0 MVP (Phases 1-4) — SHIPPED 2026-03-16</summary>
|
|
|
|
- [x] Phase 1: Foundation (2/2 plans) — completed 2026-03-15
|
|
- [x] Phase 2: Rooms and Tasks (5/5 plans) — completed 2026-03-15
|
|
- [x] Phase 3: Daily Plan and Cleanliness (3/3 plans) — completed 2026-03-16
|
|
- [x] Phase 4: Notifications (3/3 plans) — completed 2026-03-16
|
|
|
|
See `milestones/v1.0-ROADMAP.md` for full phase details.
|
|
|
|
</details>
|
|
|
|
<details>
|
|
<summary>✅ v1.1 Calendar & Polish (Phases 5-7) — SHIPPED 2026-03-16</summary>
|
|
|
|
- [x] Phase 5: Calendar Strip (2/2 plans) — completed 2026-03-16
|
|
- [x] Phase 6: Task History (1/1 plans) — completed 2026-03-16
|
|
- [x] Phase 7: Task Sorting (2/2 plans) — completed 2026-03-16
|
|
|
|
See `milestones/v1.1-ROADMAP.md` for full phase details.
|
|
|
|
</details>
|
|
|
|
## Progress
|
|
|
|
| Phase | Milestone | Plans Complete | Status | Completed |
|
|
|-------|-----------|----------------|--------|-----------|
|
|
| 1. Foundation | v1.0 | 2/2 | Complete | 2026-03-15 |
|
|
| 2. Rooms and Tasks | v1.0 | 5/5 | Complete | 2026-03-15 |
|
|
| 3. Daily Plan and Cleanliness | v1.0 | 3/3 | Complete | 2026-03-16 |
|
|
| 4. Notifications | v1.0 | 3/3 | Complete | 2026-03-16 |
|
|
| 5. Calendar Strip | v1.1 | 2/2 | Complete | 2026-03-16 |
|
|
| 6. Task History | v1.1 | 1/1 | Complete | 2026-03-16 |
|
|
| 7. Task Sorting | v1.1 | 2/2 | Complete | 2026-03-16 |
|